  • Power (Pn) : 3500 kW
    Gross Head (Hg) : 260 m
    Flow (Qn) : 1.75 m3/s
    Location : Thermorema, Sperchiada Fthiotida, Greece

    Participation : ECEN is the main shareholder of the project, completed the licensing process and all necessary initial technical studies, participated in the financing, equipment orders and construction of the project. Then, undertook fully and completed the expansion project of 1,950 kW to 3,500 kW. ECEN, also made subsequent improvement works. Currently is responsible for the maintenance and operation of the power plant.

    SHPP THERMOREMA
    SHPP THERMOREMA
  • SHPP THERMOREMA

    ECEN is the main shareholder of the project, completed the licensing process and all necessary initial technical studies, participated in the financing, equipment orders and construction of the project. Then, undertook fully and completed the expansion project of 1,950 kW to 3,500 kW. ECEN, also made subsequent improvement works. Currently is responsible for the maintenance and operation of the power plant.

    Power (Pn) : 3500 kW
    Gross Head (Hg) : 260 m
    Flow (Qn) : 1.75 m3/s
    Location : Thermorema, Sperchiada Fthiotida, Greece

  • Power (Pn) : 950 kW
    Gross Head (Hg) : 130 m
    Flow (Qn) : 950 l/s
    Location : Kakorema, Paleokastron, Fthiotida, Greece

    Participation : ECEN is the main shareholder of the project, completed the licensing process and all necessary technical studies. ECEN completed the design, financing and construction of the project, which was launched within six months of starting works. At the present, ECEN is responsible for the maintenance and operation of the power plant.

    SHPP KAKOREMA
    SHPP KAKOREMA
  • SHPP KAKOREMA

    ECEN is the main shareholder of the project, completed the licensing process and all necessary technical studies. ECEN completed the design, financing and construction of the project, which was launched within six months of starting works. At the present, ECEN is responsible for the maintenance and operation of the power plant.

    Power (Pn) : 950 kW
    Gross Head (Hg) : 130 m
    Flow (Qn) : 950 l/s
    Location : Kakorema, Paleokastron, Fthiotida, Greece

  • Power (Pn) : 1950 kW
    Gross Head (Hg) : 90 m
    Flow (Qn) : 2700 l/s
    Location : Kastoniotiko, Kastania, Trikala, Greece

    Participation : ECEN was initially the main shareholder of the project and then withdrew. Closure of the permitting process and all necessary initial technical studies was done from the company. ECEN also participated in the funding process, ordering equipment and construction.

    SHPP KASTANIOTIKO
    SHPP KASTANIOTIKO
  • SHPP KASTANIOTIKO

    ECEN was initially the main shareholder of the project and then withdrew. Closure of the permitting process and all necessary initial technical studies was done from the company. ECEN also participated in the funding process, ordering equipment and construction.

    Power (Pn) : 1950 kW
    Gross Head (Hg) : 90 m
    Flow (Qn) : 2700 l/s
    Location : Kastoniotiko, Kastania, Trikala, Greece

  • Power (Pn) : 850 kW
    Gross Head (Hg) : 245 m
    Flow (Qn) : 400 l/s
    Location : Pougkakia, Fthiotida, Greece

    Participation : ECEN was the main shareholder of the project and then withdrew. Our company completed the licensing process and all necessary initial technical studies. ECEN also participated in the funding process, ordering equipment and construction.

    SHPP POUGKAKIA
    SHPP POUGKAKIA
  • SHPP POUGKAKIA

    ECEN was the main shareholder of the project and then withdrew. Our company completed the licensing process and all necessary initial technical studies. ECEN also participated in the funding process, ordering equipment and construction.

    Power (Pn) : 850 kW
    Gross Head (Hg) : 245 m
    Flow (Qn) : 400 l/s
    Location : Pougkakia, Fthiotida, Greece

Copyright © Ecen. All right reserved. Powered by : iDreams