Power (Pn) : 3500 kW
Gross Head (Hg) : 260 m
Flow (Qn) : 1.75 m3/s
Location : Thermorema, Sperchiada Fthiotida, GreeceParticipation : ECEN is the main shareholder of the project, completed the licensing process and all necessary initial technical studies, participated in the financing, equipment orders and construction of the project. Then, undertook fully and completed the expansion project of 1,950 kW to 3,500 kW. ECEN, also made subsequent improvement works. Currently is responsible for the maintenance and operation of the power plant.
SHPP THERMOREMA -
Power (Pn) : 950 kW
Gross Head (Hg) : 130 m
Flow (Qn) : 950 l/s
Location : Kakorema, Paleokastron, Fthiotida, GreeceParticipation : ECEN is the main shareholder of the project, completed the licensing process and all necessary technical studies. ECEN completed the design, financing and construction of the project, which was launched within six months of starting works. At the present, ECEN is responsible for the maintenance and operation of the power plant.
SHPP KAKOREMA -
Power (Pn) : 1950 kW
Gross Head (Hg) : 90 m
Flow (Qn) : 2700 l/s
Location : Kastoniotiko, Kastania, Trikala, GreeceParticipation : ECEN was initially the main shareholder of the project and then withdrew. Closure of the permitting process and all necessary initial technical studies was done from the company. ECEN also participated in the funding process, ordering equipment and construction.
SHPP KASTANIOTIKO -
Power (Pn) : 850 kW
Gross Head (Hg) : 245 m
Flow (Qn) : 400 l/s
Location : Pougkakia, Fthiotida, GreeceParticipation : ECEN was the main shareholder of the project and then withdrew. Our company completed the licensing process and all necessary initial technical studies. ECEN also participated in the funding process, ordering equipment and construction.
SHPP POUGKAKIA
ECEN is the main shareholder of the project, completed the licensing process and all necessary initial technical studies, participated in the financing, equipment orders and construction of the project. Then, undertook fully and completed the expansion project of 1,950 kW to 3,500 kW. ECEN, also made subsequent improvement works. Currently is responsible for the maintenance and operation of the power plant.
Power (Pn) :
3500 kW
Gross Head (Hg) :
260 m
Flow (Qn) :
1.75 m3/s
Location :
Thermorema, Sperchiada Fthiotida, Greece
ECEN is the main shareholder of the project, completed the licensing process and all necessary technical studies. ECEN completed the design, financing and construction of the project, which was launched within six months of starting works. At the present, ECEN is responsible for the maintenance and operation of the power plant.
Power (Pn) :
950 kW
Gross Head (Hg) :
130 m
Flow (Qn) :
950 l/s
Location :
Kakorema, Paleokastron, Fthiotida, Greece
ECEN was initially the main shareholder of the project and then withdrew. Closure of the permitting process and all necessary initial technical studies was done from the company. ECEN also participated in the funding process, ordering equipment and construction.
Power (Pn) :
1950 kW
Gross Head (Hg) :
90 m
Flow (Qn) :
2700 l/s
Location :
Kastoniotiko, Kastania, Trikala, Greece
ECEN was the main shareholder of the project and then withdrew. Our company completed the licensing process and all necessary initial technical studies. ECEN also participated in the funding process, ordering equipment and construction.
Power (Pn) :
850 kW
Gross Head (Hg) :
245 m
Flow (Qn) :
400 l/s
Location :
Pougkakia, Fthiotida, Greece